2016年10月26日星期三

The connection method of deep well submersible pump before delivery

Wells with submersible pump factory are generally not only lead to cable, users need to another when installation cable, so it is important to note that when I answer the cable correctly, or has a great influence on the use of submersible pump.
The connection method of deep well submersible pump
1, stripping pump cable outer sheath and the main insulation layer, with copper wire 35-40 mm, conical rubber, that are close to the core part of the line core the oxide layer on the polished clean, and use alcohol wipe wire core (had better use hydrochloric acid) and to bind up insulation, sheath layer and makes it dry naturally.
2, 1) power cable joint (2) PVC adhesive tape (3) the viscosity butyl rubber band 4) phi 1 mm wire 5) solder 6) leads to cable
3, ready to 500 w electric, rosin, solder, LMM bare copper wire and electrical tape.
4, even with bare copper wire, tighten the cable core, with electric heating, tin, requirements, infiltration. With a file repair flat welding part (there is no burr and pointed shuttle), and once again with alcohol to wipe clean to bind part, dry. 5, first half overlapping with self-adhesive butyl tape package three layers, and gradually to the external extension of wire core. Must put tape stretch 200% when bandaging, outer half a lap with PVC glue again three layers, also gradually extend outward, guarantee the bandage part not shorter than 200 mm.
6, three core cable joint three joint position should be staggered in turn a certain distance, prevent short circuit.
7, which leads to the cable for the heaving line connection method
1) cable after pick up head shake test cable and motor (no water) insulation resistance, the value of not less than 150 ohms,
Shake again after 2) motor with full water test of the motor winding insulation resistance shall be not less than 40 ohms,
3) electricity test steering (less than 2 seconds). Make sequential position tag,
4) start the well: the next well continuous wave measuring insulation resistance at the same time observation of the change in case the wall hanging broken cable insulation skin, if it is found that the insulation level fell sharply to 0.5 ohms to unit to be brought to detect when the following reasons. If no accident, the well completion can pass about the steps in front of the boot commissioning.